Automatic scheduled start and stop of gas generators at a Queensland gas-fired power station, so the plant can be run outside manned hours. Operators now schedule up to two runs per day from SCADA, and management can check scheduled hours remotely on the enterprise historian.

What We Did

  • Development of the functional description specification
  • Reverse-engineering of the legacy PLC project (Schneider Concept)
  • CitectSCADA development for operator scheduling
  • Reporting of scheduled hours to the enterprise historian (PI Vision)
  • Remote installation and commissioning